How Much Does Post-Construction Cleaning Cost per Square Foot?

At the national mean janitor wage, a rough and final pass on new construction runs about $0.17 a square foot and a full four-phase clean about $0.24. Here is the arithmetic, phase by phase, and the state spread.

Concrete and cable trays inside a transit station interior under construction
Photo: Los Angeles County Metropolitan Transportation Authority / Wikimedia Commons (public domain)

A post-construction clean of an office-type building costs about $0.17 a square foot for a rough pass and a final pass together, using the national mean janitor wage of $18.64 an hour from the Bureau of Labor Statistics' May 2025 survey. On 10,000 square feet that is 50 cleaner-hours and a bid of roughly $1,750. Add a trade-waste sweep-out and one return visit after the punch list and the same floor comes to about $0.24 a square foot, or $2,430.

Three numbers produce that answer: the hourly wage, the square feet your crew covers in an hour, and the share of the price that goes to labour. The wage is measured. The other two are yours to set, and this piece shows every step so you can drop in your own.

What the hourly figure is built on

The BLS Occupational Employment and Wage Statistics put the national mean for janitors and cleaners (SOC 37-2011) at $18.64 an hour in May 2025, or $38,760 a year. That is a wage, not a cost. Loaded at 1.22 for FICA, federal and state unemployment insurance and workers' compensation — the same 22% used in our per-square-foot model for office cleaning — an hour of production costs $22.74.

The Quarterly Census of Employment and Wages is the reality check. Private firms in NAICS 561720 paid an average of $664 a week in the first quarter of 2026 across 1,060,484 jobs, up $20, or 3.1%, on a year earlier. At 40 hours that is $16.60 an hour, below the OEWS mean, because this work is dominated by part-time shifts and short weeks. If your payroll looks like the QCEW line, use $16.60 as your starting point instead.

How many square feet a cleaner covers, by phase

Post-construction work is four different jobs sold as one, and they run at very different speeds. The rates below are planning rates, not measurements: they assume an empty floor, reasonable access, and a crew that has done this before.

PhaseSq ft per cleaner-hourHours per 1,000 sq ftLabour at $22.74/hrPrice at 65% labourPer sq ft
Trade-waste sweep-out1,2000.83$18.95$29.15$0.029
Rough clean (dust, stickers, fixtures)6001.67$37.90$58.31$0.058
Final detail (glass, frames, sills, floors)3003.33$75.80$116.62$0.117
Punch-list touch-up9001.11$25.27$38.87$0.039

The 65% labour share is an assumption, and a conservative one for this trade: post-construction carries more consumables, more machine hours and more debris hauling than nightly office work, so if anything labour sits lower and the price per square foot sits higher. Substitute your own ratio and the table still works.

How long the job actually takes

Rough plus final on 10,000 square feet is 50 cleaner-hours. That is one cleaner for five ten-hour days, two cleaners for two and a half days, or three cleaners and a wasted week waiting for the glass to be installed. The detail pass is 33 of those 50 hours — two thirds of the money is in the last, slowest step, which is exactly the step that gets squeezed when a general contractor asks for a discount.

What the same floor costs once it is open

Nightly office cleaning on that square footage runs about $0.242 a square foot per month at the national mean wage, five nights a week. A $0.175 post-construction clean is therefore worth roughly three weeks of routine service. That comparison is the fastest way to sanity-check any post-construction bid: if you are quoting less than a month of nightly cleaning for a full rough and final on new construction, you are quoting a loss.

Where post-construction bids go wrong

Almost nothing that goes wrong on these jobs scales with square footage, which is why a rate built only from square footage is fragile.

Dust above hand height. Wiping walls to eight feet rather than four doubles the surface without changing the floor area. Measure ceiling height before you price, and price the vertical surface separately.

Window film and stickers. Protective film on frames and glass is slow, hand work. Time it on one window, multiply by the count, and show that line separately in the bid.

Debris. Construction waste is priced per load by your hauler. Get the number, put it in the bid as its own line, and do not absorb it into a rate per square foot.

Other trades still working. If the electricians are not finished, you will clean the same corridor twice. Write the access condition into the scope — the 12 lines a janitorial bid needs include it.

The punch-list return. Price it as a minimum call-out. Four hours at the national loaded rate is 4 × $22.74, or $91 of labour, which is about $140 of price at a 65% labour share. Two unplanned returns will eat the margin on a 10,000-square-foot job.

The floor at handover. Whether you hand over scrub-and-recoat or a full strip and finish changes the number more than any other line. Floor-care costs per square foot run from $0.22 to $0.38 on their own.

The state spread

The same two-phase job, priced with the same hours and the same 65% labour share, moves by more than 50% across state lines because the wage does.

StateMean wage, May 2025Loaded at 1.22Two-phase price per sq ft
Washington$22.79$27.80$0.214
Massachusetts$21.75$26.54$0.204
New York$21.55$26.29$0.202
California$21.25$25.93$0.199
Colorado$20.11$24.53$0.189
Illinois$19.59$23.90$0.184
Ohio$18.06$22.03$0.169
Florida$16.86$20.57$0.158
Texas$16.29$19.87$0.153
Alabama$15.51$18.92$0.146
Mississippi$14.32$17.47$0.134

The rate sheet you saved in 2020 is 30% short

The producer price index for janitorial services (NAICS 561720) stood at 189.663 in October 2026 against 145.5 in December 2019 — up 30.4%. Over the same stretch the consumer price index rose 31.3%, from 256.974 to 337.511. A $0.12 post-construction rate from 2019 needs to be $0.156 now just to stand still, before any change in your own coverage rates.

How to check all of it in an afternoon

Time the first 1,000 square feet of the next job with a stopwatch, phase by phase, and put the real numbers in the table above. Count fixtures rather than rooms when you price the wet areas — the method is the same one behind our restroom production rates — and load the wage with your own workers' compensation rate, not the national 22%. The arithmetic is simple enough that the only real risk is bidding from memory.

About the author

Alex V.

Alex came to The Cleaning Trade after years of writing for online publications. He covers the business side of commercial cleaning: how contracts are bid and won, what crews are paid, and the rules that shape the work. Away from the desk, he's a keen distance runner.

Newsletter

Get new stories by email.

More from The Cleaning Trade

Nov 28, 2026

What Commercial Cleaning Equipment and Supplies Cost: The Per-Hour Arithmetic Behind a Floor Machine

Nov 27, 2026

How Much Does Commercial Office Cleaning Cost per Month?

Nov 26, 2026

What Should a Commercial Cleaning Contract Renewal Cost in 2027?

Nov 20, 2026

How Much Does a Janitorial Supervisor Cost? The Pay, the Span, and the Line It Adds to a Bid